Field documentation
How to Document Hidden Roof Decking Damage After Tear-Off
Give the finding a location and an ID while the deck is exposed. Link that ID to the photos, the measured quantity, the signed scope and any approved change so the office and crew can work from the same record.
By the RooferForms editorial team
1. Capture the finding before it is covered
Have the crew follow the site safety plan and notify the project lead. From a safe work position, record the date, roof plane, nearest landmark and the visible condition. Give the finding an ID such as D-01. Take an overview showing where it is, a photo of the affected area and a detail with scale where safe. Keep the original files and list their IDs in the log.
Describe what you can see, such as separated plywood layers at a seam. Note any boundary that is still concealed and label the quantity as estimated if it cannot yet be verified. Refer suspected framing damage or uncertain conditions to the appropriate qualified person before defining the work.
2. Compare the finding with the signed scope
Check whether the agreement already includes the work, sets an allowance or unit price, or requires a separate quote. Log the observed area separately from the proposed replacement quantity. For a per-sheet price, show the number of proposed sheets, how many the base scope already includes, the billable difference and the rate. Record the schedule impact and any items still pending review.
3. Record approval and pass the revision to the crew
For work that requires a change, send the affected location, photo IDs, scope, price and schedule impact to the authorized customer contact. Keep the approved revision and record who approved it and when. While approval is pending, keep the added work marked pending and follow the site plan for safety and temporary protection. If the quantity changes again, record the difference and follow the applicable approval process before proceeding with the revised extra work.
Give the crew the approved location and quantity. Before covering the work, save the completion photos under the same finding ID and record the quantity actually installed. Keep the original scope, approved change and photo log together for closeout.
Worked example from photo log to approval
Fictional project RF-218. The quantities and rates illustrate the record only.
- Finding D-01
- Plane B, just upslope of the rear eave. Three exposed plywood sheets show separated layers along their edges. Photos B-01, B-02 and B-03 show the plane, affected sheets and seam detail.
- Quantity and price
- Replace three verified sheets. Signed scope S-01 includes one sheet and sets an additional rate of $120 per sheet. Two additional sheets × $120 adds $240 in this example. Allow two extra hours.
- Approval and closeout
- Customer approved CO-02 revision 1 in writing at 10:40 a.m. The crew received the approved three-sheet scope, logged three sheets installed and filed photos B-04 and B-05 under D-01 before covering the repair.
Put the finding on a change order
Copy the finding ID, photo references and price calculation into the free roofing change order form. The editable DOCX is available on that page.
If your team also needs a consistent way to carry the original scope and contract references through the job, see the Pro Scope & Contract Pack ($29 one time) for the shared project record, editable scope and contract draft, and handoff checklist.
Field reference: Trust Roofing’s project documentation training. Follow the signed agreement, site safety plan and applicable project requirements for your job.