How to Handle a Short or Partial Roofing Material Delivery

Check the purchase order, the quantity expected on this truck and the quantity you actually count. A planned split delivery leaves a balance on the order. A short shipment leaves a discrepancy on this delivery. Record both so the supplier and crew know what is still due.

By the RooferForms editorial team

1. Match the shipment to the purchase order

Pull up the approved purchase order (PO), the supplier’s shipment confirmation and the delivery ticket. Check the job address, PO line, product code, color and unit of measure. Count bundles against bundles and pieces against pieces. Check accessories such as starter and ridge cap against their own order lines. If the ticket and shipment confirmation disagree, record both and ask the supplier to reconcile them.

Keep separate counts for the units physically present and the units you can release to the crew. Record any damage, wrong product or unverified items separately, with label photos where practical. Hold questionable items for review under the site’s receiving process.

2. Record the short count and assign follow-up

Where practical, record the actual count and any visible issues on the delivery ticket before acknowledging receipt. Save a copy with the PO line, date and supporting photos. If you can only verify part of the load at handoff, note what you checked and follow the supplier’s reporting process for issues found later.

Ask the supplier to confirm the remaining quantity and the next delivery or pickup date in writing. Assign someone to follow up and tell the crew lead which work depends on the missing material. Keep the crew’s need date separate from the supplier’s confirmed date. Route any proposed substitution through the project’s approval process before release.

Worked example with two delivery tickets

Fictional project RF-312. PO-312, line 04, calls for 60 bundles of the same shingle SKU and color. The supplier planned 40 on the first truck and 20 on the second.

First truck · ticket DT-01
Ticket says 40 bundles. The crew counts 38 matching bundles in good condition. Record 2 short on DT-01 and 38 received against the PO. The open balance is 22 bundles, made up of the planned 20 plus the 2 missing from the first truck.
Supplier follow-up
The project coordinator sends the ticket and count to the supplier. The supplier confirms 22 bundles on the second truck. The coordinator records the confirmed date and alerts the crew lead.
Second truck · ticket DT-02
The crew verifies 22 matching bundles in good condition. Add them to the 38 already received. The cumulative receipt is 60, the open balance is zero, and the coordinator closes the issue after filing both tickets.

Update the material list after each truck

Use the free roofing material list XLSX to keep the PO reference, ticket numbers, status and next action together. In the example, enter 38 cumulative received order units after DT-01, then update that field to 60 after DT-02. Keep the per-truck counts in the ticket records. The worksheet variance compares cumulative receipts with the order, so keep the first truck’s two-bundle discrepancy in your notes until it is resolved.